Annual Report for the year ended 30 June 2002
Departmental operations (continued)
Output Class D3 - Management of equipment procurement
Project financial performance
For the year ended 30 June 2002
Project payments capitalised against Crown appropriations in 2001/02, and recoveries from New Zealand Defence Force, were: (see table below):
Expenditure |
Recoveries |
||||
|---|---|---|---|---|---|
| 2001/02 Main estimates $000 |
2001/02 Supp. estimates $000 |
30/6/2002 Actual $000 |
2001/02 Supp. estimates $000 |
30/6/2002 Actual $000 |
|
| ANZAC Ships | 38,883 | 47,638 | 32,944 | 37,336 | 37,336 |
| Maritime helicopter | 28,705 | 63,704 | 45,787 | 81,170 | 81,170 |
| Kestrel - P3 Orion rewing | 7,954 | 2,050 | 2,050 | 3,332 | 3,332 |
| P-3 Orion autopilot | 510 | 3,921 | 2,531 | 98 | 1,446 |
| RNZN Bridge Simulator | - | 76 | - | 10 | 10 |
| Light armoured vehicles | 28,140 | 5,944 | 4,318 | 86,497 | 86,497 |
| Tactical communications | 60,334 | 54,028 | 40,469 | 70,144 | 70,144 |
| Other projects | 5,807 | - | 20 | 1,484 | 137 |
| GST on imported goods and NZ payments | 14,158 | 35,424 | 34,350 | - | - |
| Total | 184,491 | 212,785 | 162,469 | 280,071 | 280,072 |
- Prices agreed for new projects approved by the Government during the financial year have been based on a competitive tender process, and contract awards have been subjected to consideration of through-life costs, quality, delivery schedule and local industrial participation.
Potential risks for all projects have been identified together with corrective actions required or taken.
All payments made have been at the contracted prices to the correct suppliers upon the achievement of agreed milestones.
ISO 9001 certification has been maintained.
Financial performance (GST exclusive)
For the year ended 30 June 2002
| 30/6/2001 Actual $000 | 30/6/2002 Actual $000 |
30/6/2002 Main estimates $000 |
30/6/2002 Supp. estimates $000 |
|
|---|---|---|---|---|
| Revenue | ||||
| Crown | 3,332 | 3,138 | 3,356 | 3,138 |
| Other | 7 | 1,073 | - | 1,114 |
| Total revenue | 3,339 | 4,211 | 3,356 | 4,252 |
| Expenditure | 3,217 | 4,002 | 3,356 | 4,252 |
| Surplus /(deficit) | 122 | 209 | - | - |
The appropriation (GST inclusive) for this output class was increased by $1,008,000 for (see table below):
| $(000) | |
|---|---|
| C130 aircraft Life of Type Study, funded by New Zealand Defence Force through Revenue Other | 1,114 |
| Expense transfer of tender phase costs for Light Operational Vehicles from 2001/02 to 2002/03 | (218) |
| GST change on above adjustments | 112 |
| Total | 1,008 |