Annual Report for the year ended 30 June 2005
Part 3: Departmental financial statements (continued)
Output Class - Management of equipment procurement
| Financial summary of pre-acquisition costs charged to departmental output class - Management of equipment procurement in 2004/05 (GST exclusive) | ||
|---|---|---|
$ |
||
| Budget for pre-acquisition costs | 163,172 | |
| Expenditure to 30 June 2005 | 163,172 | |
| Financial summary of project costs charged to non-departmental appropriations as at 30 June 2005 (GST inclusive) | ||
$ |
||
| Project approval | 373,069,314 | |
| Foreign exchange variances to date and forecast to complete | (26,024,279) | |
| GST | 46,633,667 | |
| Total approved cost | 393,678,702 | |
| GST exclusive | ||
| Expenditure to 30 June 2004 | - | |
| Expenditure 2004/05 | 65,617,789 | |
| Future commitments and forecasts | 280,869,126 | |
| 346,486,915 | ||
| GST | ||
| GST to 30 June 2004 | - | |
| Expenditure 2004/05 | 325,148 | |
| Future commitments and forecasts | 46,441,712 | |
| 46,766,860 | ||
| Total forecast cost to complete | 393,253,775 | |
- Foreign exchange variances at 30 June 2005 are favourable by $26.024 million due to the purchase rates of the USD currency being better than the USD exchange rate used in the Cabinet paper for financial approval.
USD approval rate = 0.6107
USD forecast average rate = 0.6633 - Commitments and forecasts are valued using an average exchange rate of forward contracts still to be settled, plus the actual exchange rates for currencies in the bank. The exchange rate used to calculate commitments and forecasts at 30 June 2005 was USD = 0.6600.
| Financial summary of project costs charged to non-departmental appropriations as at 30 June 2005 (GST inclusive) | ||
|---|---|---|
$ |
||
| Project approval | 580,296,353 | |
| Foreign exchange variances to date and forecast to complete | 14,703,406 | |
| GST | 72,537,044 | |
| Total approved cost | 667,536,803 | |
| GST exclusive | ||
| Expenditure to 30 June 2004 | 563,503,741 | |
| Expenditure 2004/05 | 21,520,539 | |
| Future commitments and forecasts | 9,231,262 | |
| 594,255,542 | ||
| GST | ||
| GST to 30 June 2004 | 45,071,115 | |
| Expenditure 2004/05 | 7,167,154 | |
| Future commitments and forecasts | 52,631 | |
| 52,290,900 | ||
| Total forecast cost to complete | 646,546,442 | |
- Foreign exchange variances at 30 June 2005 are unfavourable by $14.703 million due to the purchase rates for the CAD and USD currencies being less than the CAD and USD exchange rates used in the Cabinet paper for financial approval.
CAD approval rate = 0.6600
CAD forecast average rate = 0.6490
USD approval rate = 0.4400
USD forecast average rate = 0.4247 - Commitments and forecasts are valued using an average exchange rate of forward contracts still to be settled, plus the actual exchange rates for currencies in the bank. The exchange rate used to calculate commitments and forecasts at 30 June 2005 were CAD = 0.8413 and USD = 0.6600.
| Financial summary of project costs charged to non-departmental appropriations as at 30 June 2005 (GST inclusive) including approval for additional funding | ||
|---|---|---|
$ |
||
| Project approval | 220,603,000 | |
| Foreign exchange variances to date and forecast to complete | (12,623,885) | |
| GST | 27,575,000 | |
| Total approved cost | 235,554,115 | |
| GST exclusive | ||
| Expenditure to 30 June 2004 | 108,233,771 | |
| Expenditure 2004/05 | 236,460 | |
| Future commitments and forecasts | 99,365,445 | |
| 207,835,676 | ||
| GST | ||
| GST to 30 June 2004 | 13,048,133 | |
| Expenditure 2004/05 | 6,959 | |
| Future commitments and forecasts | 14,520,002 | |
| 27,575,094 | ||
| Total forecast cost to complete | 235,410,770 | |
- Foreign exchange variances at 30 June 2005 are favourable by $12.624 million due to the purchase rates for USD currency being better than the USD exchange rate used in the Cabinet paper for financial approval.
USD approval rate = 0.54251
USD forecast average rate = 0.5901 - Commitments and forecasts are valued using an average exchange rate of forward contracts still to be settled, plus the actual exchange rates for currencies in the bank. The exchange rate used to calculate commitments and forecasts at 30 June 2005 was USD = 0.6600.
| Financial summary of project costs charged to non-departmental appropriations as at 30 June 2005 (GST inclusive) | ||
|---|---|---|
$ |
||
| Project approval | 119,223,000 | |
| Foreign exchange variances to date and forecast to complete | 4,786,625 | |
| GST | 14,903,000 | |
| Total approved cost | 138,912,625 | |
| GST exclusive | ||
| Expenditure to 30 June 2004 | 118,801,182 | |
| Expenditure 2004/05 | 1,560,436 | |
| Future commitments and forecasts | 3,456,544 | |
| 123,818,162 | ||
| GST | ||
| GST to 30 June 2004 | 11,205,187 | |
| Expenditure 2004/05 | 304,275 | |
| Future commitments and forecasts | 3,386,452 | |
| 14,895,914 | ||
| Total forecast cost to complete | 138,714,076 | |
- Foreign exchange variances at 30 June 2005 are unfavourable by $4.787 million due to the purchase rates for USD currency being less than the USD exchange rates used in Cabinet paper for financial approval.
USD approval rate = 0.4300
USD forecast average rate = 0.4126 - Commitments and forecasts are valued at an average of the exchange rate of forward contracts still to be settled, plus the actual exchange rates for currencies in the bank. The exchange rate used to calculate commitments and forecasts at 30 June 2005 was USD = 0.6600.
| Financial summary of project costs charged to non-departmental appropriations as at 30 June 2005 (GST inclusive) | ||
|---|---|---|
$ |
||
| Approved contract at base rates |
938,949,321 | |
| Approved escalations at base rates | 252,391,118 | |
| Foreign exchange variances to date and forecast to complete |
125,151,984 | |
| GST | 153,808,491 | |
| Total approved cost | 1,470,300,914 | |
| GST exclusive | ||
| Expenditure to 30 June 2004 | 1,241,795,590 | |
| Expenditure 2004/05 | 840,089 | |
| Future commitments and forecasts | 500,000 | |
| 1,243,135,679 | ||
| GST | ||
| GST to 30 June 2004 | 157,476,992 | |
| Expenditure 2004/05 | 1,589 | |
| Future commitments and forecasts | - | |
| 157,478,581 | ||
| Total forecast cost to complete | 1,400,614,260 | |
- The ANZAC Ship approval was stated in 1989 base exchange rates against a basket of currencies. A Treaty with Australia recognised contract escalation and currency variances, and agreed the methodologies for calculation.

