Output Class - Management of equipment procurement (continued)

Annual Report for the year ended 30 June 2008

Contents | Previous | Next

Part 3: Statement of service performance (continued)

Output Class - Management of equipment procurement

2. The Ministry continued management of the following projects:

2.1 Replacement Helicopter Capability: Medium Utility Helicopter

This project is the acquisition of eight operational TNZA NH90 helicopters. These helicopters will be delivered to the NZDF over a period from 2010 to 2011.

Objective

In 2007/08 it was planned to:

Performance

[A] Project expenditure in 2007/08 Actual
$
Prime contract 108,323,930
Ancillary contracts (214,692)
Project management
739,387
Total net expenditure 108,848,625
GST payments 1,865
Total project expenditure in 2007/08 108,850,490
[B] Project cost summary as at 30 June 2008 Actual costs to
30 Jun 08

$
Future commitments & forecasts
$
Estimated outturn
30 Jun 08
$
Prime contract 332,452,356 362,851,712 695,304,068
Ancillary contracts 3,519,923 16,791,395 20,311,318
Project management 1,638,784 7,891,463 9,530,247
Contingency - 7,700,000 7,700,000
Project net expenditure 337,611,063 395,234,570 732,845,633
GST 23,144 96,439,748 96,462,892
Estimated project outturn     829,308,525
Effect of foreign exchange movements against the foreign exchange rates used for the Cabinet approval     37,993,962
      867,302,487
Project costs approved by Cabinet (net expenditure)     771,710,326
GST costs approved by Cabinet     96,463,791
Total costs approved by Cabinet     868,174,117

2.2 Acquisition of new vessels for the Royal New Zealand Navy

This project is for the acquisition of a multi role vessel (MRV), two offshore patrol vessels (OPV) and four inshore patrol vessels (IPV) to meet inshore and offshore requirements for maritime surface surveillance in New Zealand’s Exclusive Economic Zone in the South Pacific. The MRV will provide tactical sealift for the NZDF, support disaster relief and peace support operations, provide diplomatic and military presence, and provide training for the Royal New Zealand Navy. The MRV was delivered on 31 May 2007. A number of MRV warranty claims are being pursued with the contractor. The Crown is waiting for the contractor to offer the remaining six vessels for delivery. This is expected when the vessels are fully compliant with the appropriate requirements.

Objective

In 2007/08 it was planned to:

Performance

[A] Project expenditure in 2007/08 Actual
$
Prime contract 58,702,625
Ancillary contracts 13,509,666
Project management
2,746,509
Total net expenditure 74,958,800
GST payments 3,527,685
Total project expenditure in 2007/08 78,486,485
[B] Project cost summary as at 30 June 2008 Actual costs to
30 Jun 08

$
Future commitments & forecasts
$
Estimated outturn
30 Jun 08
$
Prime contract 415,443,336 31,710,491 447,153,827
Ancillary contracts 25,089,717 14,959,589 40,049,306
Project management 7,387,805 4,273,022 11,606,827
Contingency - 2,465,000 2,465,000
Project net expenditure 447,920,858 53,408,102 501,328,960
GST 34,587,152 27,869,674 62,456,826
Estimated project outturn     563,785,786
Effect of foreign exchange movements against the foreign exchange rates used for the Cabinet approval     (1,604,931)
      562,180,855
Project costs approved by Cabinet (net expenditure)     499,724,161
GST costs approved by Cabinet     62,466,000
Total costs approved by Cabinet     562,190,161

2.3 Acquisition of medium range anti-armour weapon for the New Zealand Army

This weapon will provide land forces with a medium range capability against armoured vehicles and other targets.

Objective

In 2007/08 it was planned to:

Performance

[A] Project expenditure in 2007/08 Actual
$
Prime contract 121,115
Ancillary contracts 193,507
Project management
33,803
Total net expenditure 348,425
GST payments 635,517
Total project expenditure in 2007/08 983,942
[B] Project cost summary as at 30 June 2008 Actual costs to
30 Jun 08

$
Future commitments & forecasts
$
Estimated outturn
30 Jun 08
$
Prime contract 16,682,406 24,902 16,707,308
Ancillary contracts 910,765 16,055 926,820
Project management 248,241 143,489 391,730
Contingency - 3,760,917 3,760,917
Project net expenditure 17,841,412 3,945,363 21,786,775
GST 1,575,069 1,406,931 2,982,000
Estimated project outturn     24,768,775
Effect of foreign exchange movements against the foreign exchange rates used for the Cabinet approval     2,069,225
      26,838,000
Project costs approved by Cabinet (net expenditure)     23,856,000
GST costs approved by Cabinet     2,982,000
Total costs approved by Cabinet     26,838,000

2.4 Acquisition of very low level air defence system for the New Zealand Army

This project will purchase an alerting and cueing system to bring the Army’s Mistral air defence system up to an improved operational standard.

Objective

In 2007/08 it was planned to:

Performance

[A] Project expenditure in 2007/08 Actual
$
Prime contract 34,608
Ancillary contracts 138,715
Project management
2,389
Total net expenditure 175,712
GST payments 19,652
Total project expenditure in 2007/08 195,364
[B] Project cost summary as at 30 June 2008 Actual costs to
30 Jun 08

$
Future commitments & forecasts
$
Estimated outturn
30 Jun 08
$
Prime contract 13,589,112 165,683 13,754,795
Ancillary contracts 335,391 334,622 670,013
Project management 260,137 - 260,137
Contingency - 131,737 131,737
Project net expenditure 14,184,640 632,042 14,816,682
GST 1,524,130 260,667 1,784,797
Estimated project outturn     16,601,479
Effect of foreign exchange movements against the foreign exchange rates used for the Cabinet approval     (538,307)
      16,063,172
Project costs approved by Cabinet (net expenditure)     14,278,376
GST costs approved by Cabinet     1,784,797
Total costs approved by Cabinet     16,063,173

2.5 Upgrade and refurbishment of C-130H aircraft for the Royal New Zealand Air Force

This project will extend the life of the Royal New Zealand Air Force C-130H Hercules aircraft by upgrading the aircraft mechanical and electrical equipment, undertaking a level of structural refurbishment work and an upgrade of communication/navigation systems.

The first aircraft is scheduled to be completed in 2008, with the final aircraft scheduled to be completed in 2011.

Objective

In 2007/08 it was planned to:

Performance

[A] Project expenditure in 2007/08 Actual
$
Prime contract 28,660,133
Ancillary contracts 120,094
Project management
1,169,360
Total net expenditure 29,949,587
GST payments 4,426,167
Total project expenditure in 2007/08 34,375,754
[B] Project cost summary as at 30 June 2008 Actual costs to
30 Jun 08

$
Future commitments & forecasts
$
Estimated outturn
30 Jun 08
$
Prime contract 184,748,086 44,870,839 229,618,925
Ancillary contracts 3,372,547 3,543,959 6,916,506
Project management 3,873,000 3,437,189 7,310,189
Contingency - 6,543,000 6,543,000
Project net expenditure 191,993,633 58,394,987 250,388,620
GST 4,669,815 27,197,185 31,867,000
Estimated project outturn     282,255,620
Effect of foreign exchange movements against the foreign exchange rates used for the Cabinet approval     3,111,430
      285,367,050
Project costs approved by Cabinet (net expenditure)     254,939,000
GST costs approved by Cabinet     31,867,000
Total costs approved by Cabinet     286,806,000

2.6 Upgrade of P-3K Orion mission systems for the Royal New Zealand Air Force

This project will upgrade the sensors, mission management systems and communication/navigation system required for the Royal New Zealand Air Force’s P-3K Orion maritime patrol aircraft to conduct surface surveillance tasks.

The first aircraft, originally scheduled to be delivered in June 2008, is now forecast to be completed in mid-2009 with the final aircraft completed in late 2011. Delays have been caused by the late delivery of the radar, and problem resolution of the integration of individual sensors and of the total integrated system.

Objective

In 2007/08 it was planned to:

Performance

[A] Project expenditure in 2007/08 Actual
$
Prime contract 12,164,082
Ancillary contracts 24,365
Project management
1,223,386
Total net expenditure 13,411,833
GST payments (562,200)
Total project expenditure in 2007/08 12,849,633
[B] Project cost summary as at 30 June 2008 Actual costs to
30 Jun 08

$
Future commitments & forecasts
$
Estimated outturn
30 Jun 08
$
Prime contract 214,280,441 88,388,275 302,668,716
Ancillary contracts 8,306,332 1,407,297 9,713,629
Project management 4,878,083 2,349,766 7,227,849
Contingency - 7,291,514 7,291,514
Project net expenditure 227,464,856 99,436,852 326,901,708
GST 870,297 45,685,348 46,555,645
Estimated project outturn     373,457,353
Effect of foreign exchange movements against the foreign exchange rates used for the Cabinet approval     41,674,400
      415,131,753
Project costs approved by Cabinet (net expenditure)     373,069,314
GST costs approved by Cabinet     46,633,667
Total costs approved by Cabinet     419,702,981

2.7 Boeing 757 Acquisition/Modification for the Royal New Zealand Air Force

This project replaces the Boeing 727 aircraft with Boeing 757 aircraft to provide greater range and payload capacity. Two aircraft have been purchased and are being operated by the Royal New Zealand Air Force in a passenger configuration. The intention is to modify them to provide a dual passenger/freight capability. Both aircraft are scheduled to be completed by 2008.

Objective

In 2007/08 it was planned to:

Performance

[A] Project expenditure in 2007/08 Actual
$
Prime contract 128,643
Ancillary contracts 3,965,752
Project management
972,487
Total net expenditure 5,066,882
GST payments 13,496
Total project expenditure in 2007/08 5,080,378
[B] Project cost summary as at 30 June 2008 Actual costs to
30 Jun 08

$
Future commitments & forecasts
$
Estimated outturn
30 Jun 08
$
Prime contract 144,668,874 14,653,089 159,321,963
Ancillary contracts 36,009,838 10,534,786 46,544,624
Project management 3,636,224 1,041,270 4,677,494
Contingency - 4,234,560 4,234,560
Project net expenditure 184,314,936 30,463,705 214,778,641
GST 13,116,089 14,459,286 27,575,375
Estimated project outturn     242,354,016
Effect of foreign exchange movements against the foreign exchange rates used for the Cabinet approval     5,825,130
      248,179,146
Project costs approved by Cabinet (net expenditure)     220,603,771
GST costs approved by Cabinet     27,575,375
Total costs approved by Cabinet     248,179,146