Defence Long-Term Development Plan (LTDP)
(October 2008 Update)
8. Projects Critical to Avoid the Failure of Policy
Joint Communications Modernisation
Below is text equivalent for the diagram illustrating the development and status of the Joint Communications Modernisation project:
- Project Initiation: Ministerial Note
- Initial Gate: Approval to Initiate
- Main Gate: Approval to Commence Acquisition
- Approval to Negotiate
- Approval to Commit
(The shaded areas indicate the stage where the project has reached - currently there are no shaded areas.)